1
00:00:04,760 --> 00:00:06,760
400 people work here.

2
00:00:06,960 --> 00:00:08,960
People have been outside the factory now for 62 days.

3
00:00:09,160 --> 00:00:11,940
Tanks are built in this factory. 

4
00:00:12,140 --> 00:00:18,440
Boilers, heat exchangers, compabloc. These types of things are made here.

5
00:00:18,800 --> 00:00:23,333
We export too. Tata Chemical, Bicon, Rasim, Reliance.

6
00:00:23,533 --> 00:00:27,533
We've put this picture of Gandhi up here because he's a symbol of our ideals.

7
00:00:27,733 --> 00:00:33,230
400 people have started the struggle with a peaceful sit-in. 

8
00:00:40,075 --> 00:00:44,909
People work here on a contract and permanent basis.

9
00:00:45,109 --> 00:00:50,100
These contract workers, some of whom have worked here for 20, 25 years, 

10
00:00:50,300 --> 00:00:52,300
haven't been thought about by the company at all. 

11
00:00:52,500 --> 00:00:54,500
They aren't given access to any facilities.

12
00:00:54,700 --> 00:00:56,700
And the difference in the wages...

13
00:00:56,900 --> 00:01:01,180
There's a big difference in the wages that the company pays.

14
00:01:01,380 --> 00:01:09,510
The contractors take out all their profits and commissions before paying the workers.

15
00:01:10,392 --> 00:01:12,686
The gap between their profits are and what the workers get is a big one.

16
00:01:12,886 --> 00:01:19,577
Wages and contracts are worked out through a system of categorisation.

17
00:01:19,777 --> 00:01:27,429
They provide us with grades: A, B, C grade, skilled, expert, senior expert.

18
00:01:27,629 --> 00:01:30,525
The highest category is senior expert.

19
00:01:30,725 --> 00:01:32,725
Senior experts get 12,000 rupees (£117 or 142 Euro).

20
00:01:34,135 --> 00:01:44,000
The experts get about 8000-9000 rupees, high skilled workers get about 7500-8000.

21
00:01:44,200 --> 00:01:50,445
The rest (A,B,C grade and helpers) get 5000-6000 rupees.

22
00:01:50,620 --> 00:01:53,285
If I was permanent I'd be making about 28,000- 30,000 rupees.

23
00:01:54,545 --> 00:01:58,639
Initially 800 contract workers worked for the company.

24
00:01:58,839 --> 00:02:02,200
The company started letting them go in dribs and drabs until 400 people were gone.

25
00:02:02,400 --> 00:02:10,647
The 400 people left thought that they could carry on and get rid of another 200 people,

26
00:02:10,847 --> 00:02:16,847
we're all vulnerable. We won't know if we'll have a job or not. So we made a union.

27
00:02:17,047 --> 00:02:19,775
Because we realised that anything could happen to us in the future. 

28
00:02:19,975 --> 00:02:21,975
So now we're ready, for opposition.

29
00:02:22,175 --> 00:02:24,175
We want permanent status.

30
00:02:24,375 --> 00:02:26,934
There are no facilities for us.

31
00:02:27,134 --> 00:02:34,000
The facilities the company provides for the permanent workers aren't available for us.

32
00:02:34,200 --> 00:02:37,600
Bonuses, we don't get those either.

33
00:02:37,800 --> 00:02:40,000
Canteen, bus, medical...

34
00:02:42,200 --> 00:02:44,802
230 workers are permanent,

35
00:02:45,002 --> 00:02:47,618
60 people on staff, they're also permanent.

36
00:02:50,100 --> 00:02:56,041
Contract workers do at least 80% of the production work for the company.

37
00:02:56,514 --> 00:03:01,406
So these permanent workers, they worked together with you, on a daily basis.

38
00:03:01,606 --> 00:03:07,501
The same work. But these workers don't speak to your now? -No

39
00:03:07,701 --> 00:03:11,479
They just leave the factory and don't say anything to you. -They don't say anything to us.

40
00:03:11,679 --> 00:03:15,211
So this is a really difficult situation. Why is it like that? For what reason?

41
00:03:15,411 --> 00:03:21,164
They just think about themselves! They don't think about us.

42
00:03:22,874 --> 00:03:27,115
What are you all doing to further the struggle?

43
00:03:27,315 --> 00:03:29,110
Lots of people have supported us.

44
00:03:29,310 --> 00:03:34,330
At least 200 people - their big leaders have come to support us.

45
00:03:34,530 --> 00:03:37,500


46
00:03:37,700 --> 00:03:41,960
Workers of tomorrow won't be able to change anything.

47
00:03:42,160 --> 00:03:47,650
The situation as it stands now: we have a case going through the labour courts,

48
00:03:49,000 --> 00:03:52,328
the talks with the company are ongoing...

49
00:03:52,528 --> 00:03:54,812


50
00:03:57,000 --> 00:04:00,678
The biggest difficulty is the fact that we're not getting any wages, nothing.

51
00:04:00,878 --> 00:04:03,487
It's been two months now.

52
00:04:03,687 --> 00:04:07,659
And the company hasn't given us any reply. That's the biggest difficulty.

53
00:04:07,859 --> 00:04:14,382
The best thing is that we're all united.

54
00:04:14,582 --> 00:04:19,332
Like friends. We can share our troubles.

55
00:04:19,532 --> 00:04:24,733
With this type of contract system, the poor remain poor.

56
00:04:24,933 --> 00:04:26,933
And the rich get richer.

57
00:04:27,133 --> 00:04:32,063
So our demand is that, for all the workers, who've given so many years to this company,

58
00:04:32,163 --> 00:04:35,814
who've sweated for the company,

59
00:04:36,014 --> 00:04:42,488
that the company should now give some thought to us, they should make us permanent,

60
00:04:42,688 --> 00:04:47,000
so that our wives and children can remain happy.
